What went well
- Goal
- Were able to add items to the sprint backlog
- Design is shaping up well
- Logged some issues that we can handle in the future (issue mitigation)
- Even with some interruption we managed the sprint time well
- Eugene is an outstanding scholar (hip hip HOORAY, hip hip HOORAY, hip hip HOORAY)
- Overall group
What didn't go well
- IE
- Things break (limited javascript tests)
- Lack of automated tests
- Not closing enough issues
Improvements?
- Logo modifications
- Qunit test coverage
|